PRJ41: Incorrect Variance Calculations (155247)



The information in this article applies to:

  • Microsoft Project 98 for Windows
  • Microsoft Project for Windows 95 4.1

This article was previously published under Q155247

SYMPTOMS

If you have a Baseline cost value between $21,474,837 and $42,949,017 with Total Cost of $0, the cost variance is calculated incorrectly.

RESOLUTION

To correct this problem, you must upgrade to Microsoft Project for Windows 95 version 4.1a. This upgrade is free to registered users and can be obtained by calling Microsoft Technical Support at (425) 635-7155.

STATUS

Microsoft has confirmed this to be a problem in the versions of Microsoft Project listed above.

This problem was corrected in Microsoft Project for Windows 95 version 4.1a.

Modification Type:MajorLast Reviewed:10/7/2003
Keywords:kbbug kbfix KB155247