PRJ: Summary Task Work/Cost Different on Crosstab Reports (130391)



The information in this article applies to:

  • Microsoft Project 2000
  • Microsoft Project 98 for Windows
  • Microsoft Project for Windows 95 4.1
  • Microsoft Project for Windows 95 4.1a
  • Microsoft Project for Windows 4.0
  • Microsoft Project for the Macintosh 4.0

This article was previously published under Q130391

SYMPTOMS

In Microsoft Project, when you print or print preview a crosstab report, summary task Cost or Work may be less than what is displayed for that summary task in a task view.

CAUSE

Summary Cost and Work is calculated differently in a crosstab report than it is in a task report or task view. In a crosstab report, Cost for a summary task includes only Fixed Cost and cost for resources assigned to that summary task, it does not include the total of it's subtasks. In addition, summary task work includes only work for resources assigned to that summary task.

Modification Type:MajorLast Reviewed:11/25/2003
Keywords:kbother kbprb KB130391